Change Order Example for Contractors: What to Include Before Work Begins

The Trusso TeamNovember 17, 20266 min read

A customer asks for one more thing. You say sure, then you keep working. Three weeks later they're disputing the invoice because nothing was ever written down. The fix isn't a lecture on why change orders matter — you already know that. The fix is having a format you can fill out in two minutes, on the job, before the work continues. Here's a complete one, field by field, followed by a shorter version for the stuff that comes up same-day.

If you want the reasoning behind markup, timing, and when a verbal okay is enough, that's covered in Change Orders 101: How to Price and Document Mid-Job Scope Changes. This post is just the paperwork, filled out.

Sample Change Order #1: Full Format, Bathroom Remodel

This is the kind of change order you'd generate for a scope change that adds real dollars and real schedule — the kind that needs a signature before anyone touches the new work.

  • Change Order #: CO-014-2 (job number 014, second change order on this job)
  • Date issued: June 9, 2026
  • Job / address: Hernandez bathroom remodel, 412 Birchwood Ln, Unit B
  • Original contract reference: Estimate #E-2231, approved May 28, 2026, total $11,400
  • Reason for change: Demo of the tub surround on June 9 exposed water-damaged subfloor behind the drain, roughly 6 sq ft, with soft spots extending to the adjacent wall stud. This was not visible during the original site visit and is not covered under the original scope.
  • Scope added: Remove and replace 6 sq ft of subfloor (3/4" plywood, treated), sister one wall stud, treat affected area with antimicrobial sealant, haul and dispose of damaged material.
  • Scope removed: None — this is added work, not a substitution.
  • Price adjustment: +$680 (labor $380, materials $180, disposal $45, 20% markup on materials and disposal per price book — total reflects actual cost plus standard markup, not a flat rate)
  • Schedule impact: Adds 1 day to the project. New estimated completion: June 14 instead of June 13.
  • Payment terms for this change: Due with final invoice, same terms as original contract. No deposit required since balance of original contract covers it.
  • Customer approval: Signature line, printed name, date. Contractor signature line, printed name, date.
  • Note field: "Work will not proceed on the exposed subfloor until this change order is signed. Remaining original scope (tile, vanity install) continues as scheduled."

That last note matters as much as the price. It tells the customer exactly what's paused and what isn't, so they don't think the whole job stopped over a $680 item.

Why Every Field Earns Its Place

Each line on that form exists because of a specific argument it prevents.

  • Change order number tied to the job number — so when you're invoicing later, you can pull every change order for that job in one search instead of digging through a folder of PDFs.
  • Reason for change, written in plain language — this is what protects you if the customer later claims you should have known about the damage. "Not visible during the original site visit" is doing real work in that sentence.
  • Scope added and scope removed as separate lines — even when nothing is removed, writing "None" closes the door on a customer later claiming something got dropped without discussion.
  • Price adjustment shown with its math, not just a total — a customer who sees labor, materials, disposal, and markup broken out is far less likely to push back than one who sees a single number with no explanation.
  • Schedule impact as its own line — price disputes are common; schedule disputes are worse, because by the time they surface, the customer has already told their boss or their in-laws a completion date you never agreed to.
  • A note field for what's paused vs. what's continuing — prevents the customer from assuming the entire crew went home.

Notice the price adjustment used the same markup logic as the original estimate — it's not a made-up number pulled from thin air to cover the surprise. If your pricing on extras doesn't match your pricing on the original scope, customers notice, and it becomes a trust issue that outlasts the job itself.

Sample Change Order #2: Same-Day Verbal-to-Written Conversion

Not every change needs the full form above. A lot of real-world extras happen in a five-minute conversation on the driveway, and the paperwork should match that pace — short, immediate, and still signed.

  • Change order #: CO-048-1
  • Date / time: July 2, 2026, 11:40 AM
  • Job: Fence staining, 88 Larkspur Ct
  • Reason: Customer walked out and asked us to also stain the small side gate and the 4-ft section of fence behind the shed, not included in original scope.
  • Scope added: Stain side gate (both faces) and 4 linear ft of rear fence section.
  • Price: +$75 flat, per posted small-add rate
  • Schedule impact: None — completed same visit
  • Approval: Verbal okay given on-site at 11:42 AM; customer texted "yes go ahead" at 11:43 AM, screenshot attached to job file; written confirmation sent same day for signature within 24 hours.

That's the whole thing. No markup breakdown, no schedule line that needs explaining, because there isn't one. What it still has: a timestamp, the customer's own words confirming approval, and a written record that exists before the invoice goes out — not reconstructed from memory three weeks later when they ask why the invoice is $75 higher than the estimate. For more on building this kind of record in the moment, see How to Document Extra Work Before Asking a Customer to Approve It.

Where This Fits on the Invoice

A change order isn't the end of the paper trail — it's the start of one. If a job ends up with three or four of these, your final invoice needs to show each one as its own line, tied back to its change order number, not folded into a vague "extra work" total. That's covered in detail in How to Invoice a Customer When a Job Has Multiple Approved Change Orders, and it's worth reading before you send the bill on any job with more than one change order attached.

Keeping the Format Consistent

The hardest part of change orders isn't writing one — it's writing one the same way every time, on every job, including the small $75 ones that feel too minor to bother with. The jobs that end in disputes are almost never the ones with a signed change order on file; they're the ones where the contractor meant to write it up later and never did.

Trusso generates change orders from the same price book you already use for estimates, so the $680 subfloor repair and the $75 gate stain both price out against rates you've already set instead of a number you're inventing on the spot. The customer signs on your phone or theirs, it attaches to the job automatically, and it shows up as its own line when you invoice — which matters most on the jobs that pick up two or three of these before they're done.