Start with fixture count and finish level to set the baseline, then add line items for demo and disposal, waterproofing, tile labor priced by the square foot, plumbing and electrical rough-in, permit fees, and a dollar allowance for whatever you find once the walls are open. A typical full gut bathroom lands between $12,000 and $35,000, and the spread exists because every one of those line items can swing wildly from job to job.
Bathroom remodels are where a lot of contractors get burned, not because they can't measure a room, but because they price the visible work and guess at everything else. A kitchen remodel has more square footage and more cabinets to keep track of, which is its own headache — see how to price a kitchen remodeling job without missing hidden costs for that version. A bathroom is smaller but denser: every square foot has plumbing, electrical, or waterproofing running through it, which is exactly why a flat per-square-foot number falls apart the moment you open a wall.
Start With Fixture Count and Finish Level
Before you touch demo or labor, decide what's going into the room. A tub-to-shower conversion, a toilet swap, and a vanity replacement is a completely different job than a full gut that relocates the toilet and adds a freestanding tub. List the fixtures first: toilet, vanity and sink, tub or shower (or both), tile, lighting, exhaust fan, and any heated flooring or accessories. Then assign a finish tier to each one — builder-grade, mid-range, or high-end — because the fixture line alone can run from $150 for a basic toilet to $1,200 for one with a bidet seat, and from $400 for a stock vanity to $3,500 for a custom one.
This is also where you find out if the customer's budget matches their Pinterest board. If they're describing a spa shower with a rain head, a bench, and a linear drain but budgeting like it's a tub-to-shower swap, better to surface that gap during the estimate conversation than after you've already quoted a number.
Demo and Disposal
Tearing out an old bathroom is cheap in materials and expensive in time, especially if there's tile on the floor, tile on the walls, and a cast iron tub that two guys have to carry down a flight of stairs. Budget demo as its own line, typically $1,000 to $3,000 for a standard hall bath, more if there's a tub to remove whole or asbestos-era tile that needs special handling. Add a dumpster or haul-away fee separately — don't bury it in labor, because it's one of the easiest things for a customer to question later if it isn't broken out.
Waterproofing Before Tile Goes On
This is the step homeowners never think about and the one that causes callbacks years later if it's skipped. Cement board or a liquid waterproofing membrane on shower walls, a pan liner or pre-sloped foam pan under the shower floor, and proper flashing around the niche and curb all need to be priced as their own line, not absorbed into tile labor as an afterthought. For a standard shower, plan on $600 to $1,500 for materials and labor combined, more for a curbless or linear-drain shower where the slope work is more involved.
Price Tile Labor by the Square Foot
Tile is the line item customers will scrutinize the most because they can see the tile they picked online. Price labor by the square foot and keep floor, wall, and shower tile separate, since shower walls take longer per foot than open floor due to cuts, corners, and niches. A realistic range is $8 to $15 per square foot for floor tile labor and $12 to $22 per square foot for shower walls, with large-format tile, herringbone patterns, or natural stone pushing toward the top of that range. Add 10-15% material waste on top of the measured square footage — the same logic covered in how much material waste should you build into an estimate, which applies just as much to a 5x8 bathroom as it does to a whole-house flooring job.
Plumbing and Electrical Rough-In
If fixtures are staying in the same location, rough-in costs stay modest — mostly reconnecting supply lines, swapping valves, and running a new drain connection. If the toilet is moving, the vanity is relocating to a different wall, or the shower is growing from a 32-inch stall to a 60-inch walk-in, you're paying for new drain and vent lines, which means opening the floor and possibly the ceiling below. Electrical follows the same pattern: a straight fixture swap is a quick in-and-out, while adding a vanity light circuit, a heated floor mat, or GFCI-protected outlets to meet current code can add a few hundred dollars in materials and an hour or two of labor per circuit. Price plumbing and electrical as separate lines so the customer can see what moving fixtures actually costs versus leaving them in place.
Permits
Most jurisdictions require a permit for any job that touches plumbing rough-in, electrical circuits, or structural changes, and bathroom remodels usually hit at least one of those. Permit fees typically run $150 to $500 depending on the municipality and scope, and the inspection trips add a day or two to the schedule that the customer should know about upfront. Skipping the permit to save money is a bad trade for both of you — it shows up at resale, and it's the first thing an insurance adjuster asks about if there's ever water damage.
The Allowance for What's Behind the Wall
This is the line that separates a profitable bathroom remodel from one that eats your margin. Old houses hide rot behind tub surrounds, subfloor damage under toilets that have been leaking slowly for years, and galvanized supply lines that crumble the moment you touch them. Build a dedicated allowance into the estimate — not a vague buffer, but a stated dollar amount, typically $500 to $2,000 depending on the age of the house — and explain to the customer exactly what it covers: subfloor repair, minor framing, or supply line replacement discovered after demo. This is the same discipline covered in how much contingency should contractors add to an estimate, and a bathroom is one of the places it matters most because you genuinely cannot see what's behind 1960s tile until it's gone.
If you find something bigger than the allowance covers, that's a change order conversation, not a surprise on the final invoice. How to document extra work before asking a customer to approve it covers how to handle that moment so it doesn't turn into a dispute.
A Sample Line-Item Breakdown
Here's a rough structure for a mid-range 100-square-foot hall bath remodel — tub-to-shower conversion, new vanity, new tile floor and shower walls, fixtures replaced in place:
- Demo and disposal: $1,800
- Waterproofing (shower pan, membrane, flashing): $900
- Tile labor, floor and shower walls (120 sq ft at $11/sq ft average): $1,320
- Tile materials with 12% waste factor: $1,100
- Plumbing rough-in and fixture connection: $1,600
- Electrical (vanity light, exhaust fan, GFCI outlets): $700
- Fixtures (toilet, vanity, shower valve and head, mirror, hardware): $2,600
- Permit and inspections: $300
- Allowance for hidden conditions: $1,200
- Labor (framing, drywall, finish carpentry, paint, cleanup): $3,400
- Overhead and profit (20% of the $14,920 subtotal): $2,984
That lands around $17,900 for a mid-range job with no major relocations. Move the toilet across the room, or go with a curbless shower and large-format porcelain slab walls, and the same square footage can push past $25,000. A gutted, re-plumbed, re-wired bathroom with a freestanding tub and custom tile work can run $35,000 or more in higher cost-of-living markets.
Give a Range, Not a Single Number Until You've Opened the Walls
Until demo is done, you're estimating a bathroom you can't fully see. It's fair — and honest — to give the customer a range on the initial estimate and tighten it once the old tile and drywall are out. How do you explain an estimate range without making a firm promise walks through how to frame that conversation so the customer understands why the number might move without feeling like you're padding it. A good site visit up front narrows that range considerably; the contractor site visit checklist is worth running through before you quote any remodel, bathroom or otherwise, so you catch the plumbing stack location and subfloor condition before you're committed to a price.
Bathroom remodels have more moving line items than almost any other residential job — fixtures, demo, waterproofing, tile, plumbing, electrical, permits, and an allowance, all before labor and markup. Trusso's estimating tools let you build each of those as its own saved line in your price book, so a bathroom quote is assembled from pieces you've already priced correctly once, rather than re-guessed from scratch every time a new lead calls. If you want to see how the numbers come together for a remodeling business specifically, the remodeling trade page breaks down how estimates, scheduling, and invoicing fit together for that kind of project.
How much does a bathroom remodel cost on average?
Most full bathroom remodels in the US run $12,000 to $35,000, with a tub-to-shower conversion or fixture refresh landing on the lower end and a full gut with relocated plumbing and high-end tile on the higher end. Regional labor rates and the age of the house move this range significantly.
Should I charge per square foot for a bathroom remodel?
Price tile labor and flooring per square foot, but price plumbing, electrical, demo, waterproofing, fixtures, and permits as separate line items. A flat per-square-foot number for the whole job hides too much variation to be accurate on a room this dense with mechanicals.
How much should I add for unknown conditions behind the walls?
Build a stated dollar allowance into the estimate, typically $500 to $2,000 depending on the age of the house, rather than a vague percentage buffer. Explain to the customer exactly what it covers — subfloor repair, minor framing, or old supply line replacement — so it doesn't look like padding.
Why does moving a toilet or shower cost so much more?
Relocating any fixture usually means running new drain and vent lines, which requires opening the floor and sometimes the ceiling below it. That's framing, plumbing, and patching work on top of the fixture swap itself, and it's one of the biggest single cost drivers in a bathroom remodel.
Do I need a permit for a bathroom remodel?
Almost always, if the job touches plumbing rough-in, electrical circuits, or structural elements, which most bathroom remodels do. Permit fees typically run $150 to $500, and skipping the permit creates problems at resale and with insurance claims if there's ever water damage.
Run your business the simple way
Try Trusso free for 14 days and send your first estimate in minutes.
Start 14-Day Free TrialKeep reading
What Is Construction Takeoff Software and Do Small Contractors Need It?
Takeoff software measures quantities—areas, lengths, counts—straight from plans so you can price a job without a tape measure and a calculator. Here's when a small contractor actually needs it.
Read articleComparisons7 Best Contractor Foreman Alternatives for General Contractors
Contractor Foreman covers a lot of ground but little of it goes deep. Here are 7 alternatives GCs switch to once they need real takeoff, sub bid-outs, or sharper scheduling.
Read article